{{ propApi.searchIcon }}
{{ propApi.closeIcon }}
Our industry
Our industry $vuetify.icons.faArrowRight
Housing industry insights
Economics Insights Data & forecasts Tailored research & analysis
Advocacy & policy
Advocacy Policy priorities Position statements Submissions
News & inspiration
Industry news Member alerts Media releases HOUSING Online
Business support
Business support $vuetify.icons.faArrowRight
Support & guidance
Ask an expert Contracts & compliance support Building & planning services Australian Standards
Member perks
Toyota vehicles The Good Guys Commercial Ampol fuel savings See all
Industry insurance
HIA Insurance Services Construction works insurance Home warranty insurance Tradies & tool insurance
For your business
Contracts Online Safety systems & solutions HIA SafeScan
Apprentices
Why host a HIA apprentice? Hire an apprentice Value for money
Resources & advice
Resources & advice $vuetify.icons.faArrowRight
Building it right
Building codes National Construction Code Australian standards See all
Building materials & products
Concrete, bricks & walls Getting products approved Use the right products for the job See all
Managing your business
Dealing with contracts Handling disputes Managing your employees See all
Managing your safety
Safety rules Working with silica See all
Building your business
Growing your business Communication for your business See all
Other subjects
Getting approval to build Sustainable homes See all
Careers & learning
Careers & learning $vuetify.icons.faArrowRight
A rewarding career
Become an apprentice Apprenticeships on offer How do I apply? Frequently asked questions
Study with us
Find a course to suit you Qualification courses Learning on demand Professional development courses
A job in the industry
Get your builder's licence Continuing Professional Development (CPD) Further your career
HIA community
HIA community $vuetify.icons.faArrowRight
Grow with us
Sign me up Become a member Member benefits Mates rates
Our podcasts
Made To Build Built Different HIA Building Australia Building the Hunter
Our initiatives
HIA Building Women Charitable Foundation GreenSmart Kitchen, bathroom & design hub
Get involved
Become an award judge Join a committee Meet our members Partner with us
Awards & events
Awards & events $vuetify.icons.faArrowRight
Awards
Awards program People & Business Awards GreenSmart Australian Housing Awards
Awards winners
Regional Award winners Australian Housing Award winners 2026 Australian Home of the Year
Industry events
Events in the next month Economic outlook HIA Made Events calendar
HIA shop
HIA shop $vuetify.icons.faArrowRight
Most popular products
National Construction Code Vol 1 & 2 Waterproofing wet areas AS 3740:2021 HIA Guide to Waterproofing HIA Guide to NCC Livable Housing Provisions
Top categories
Building codes & standards Contracts & documents Guides & manuals Safety products Signage
For your business
Contracts Online Digital Australian Standards Digital Resource Library Forecasts & data
About Contact Newsroom
$vuetify.icons.faTimes
$vuetify.icons.faMapMarker Set my location Use the field below to update your location
Address
Change location
{{propApi.title}}
{{propApi.text}} {{region}} Change location
{{propApi.title}}
{{propApi.successMessage}} {{region}} Change location

$vuetify.icons.faPhone1300 650 620

Victorian Guide to Standards and Tolerances 2026 update

Guides to Standards and Tolerances set an accepted industry standard for common workmanship and material tolerances. These standards have been revised for the first time since 2015.

Like earlier Guides, the 2026 guide reinforces its advisory role as a technical reference for assessing building work and resolving disputes, while recognising that assessments must also consider legislation, the NCC, Australian Standards, manufacturer requirements and project-specific circumstances.

When called up in contract specifications by agreement with clients it can establish criteria for acceptance of building work commencing on or after 1 August 2026.

The guideline’s language has been amended and represents a significant shift in both language and purpose from the 2015 edition. Rather than determining whether work is "defective", the revised Guide focuses on whether building work is within or outside its tolerances. It also expressly states that assigning responsibility for rectification is beyond its scope.

Consequential damage

The 2026 Guide introduces a new section on consequential damage recognising that a failure to meet the tolerances can cause damage to other building elements (e.g. waterproofing) and reinforces that consequential damage should be considered alongside the original issue where a direct link exists.

Members should undertake steps that will help reduce the likelihood of consequential damage when notified of a failure to meet the tolerances. For example, temporarily sealing a leaking roof to prevent further damage until its cause is further investigated or the roof is permanently repaired.

Normal viewing position

The 2026 Guide expands the concept of normal viewing position, which is the distance and angle from which a building element is inspected to determine whether an imperfection is visible under normal conditions of use. A notable change is that glass is now assessed from 3 metres, rather than the general 1.5 metre viewing distance applied to most building elements.

Tolerances for building elements

The 2026 Guide includes mostly minor changes to pre-determined methods, tolerances, and measurement distances for various building elements. The table below contains a comparison of the 2015 and 2026 Guidelines:

Setting Out  2015 Guide  2026 Guide 
External dimensions  L/200 or 5mm 
whichever greater
L/200 or 10mm 
whichever greater 
Internal dimensions  L/100 or 5mm 
whichever greater 
L/100 or 10mm 
whichever greater
Complex design limitation
- Does not apply to complex engineering designs including suspended, precast or tensioned slabs.
Cracks in concrete
2mm or greater

2mm or greater
Only applicable to slab on ground.

Masonry
Mortar 
NCC or contract specifications
Significantly inconsistent in colour and finishing.
Mortar repairs do not match as closely as practicable.
Mortar voids & holes  Visible from a normal viewing position
Visible from a normal viewing position and exceeds 5mm in diameter.
Base bed joint
Unexposed base bed joint exceeds 40mm
Non-faced base row visible from normal viewing position and not consistent.
Damp proof course
In accordance with NCC 
Does not extend through the entire masonry leaf.
Framing
Plumbness 
Deviates >5mm across 1.8m height 
Timber deviates >5mm over a 2m height. 
Light steel frames deviate more than height/600 or 3mm, whichever is greater.
Straightness
Deviates >4mm in any 2m length of wall 
Deviates >5mm from a 2m straight edge.
Roofing
   
Corroded metal sheets 
Unintended corrosion unless due to lack of maintenance by owner
Exposed to normal conditions and does not achieve the service life specified by manufacturer.
Sheet cuts 
  Deviates >10mm from a 2m straight edge 
Gutters water retention  Retain >10mm of water 
Retains >10mm of water and does not clear all debris that restricts flow of water.
Parapet flashings 
Minimum 3 degrees fall 
Minimum 5 degrees fall 
Exposed PVC/PE pipes 
- Not protected/shielded from direct sunlight or provided with UV protection. 
Plumbing
Water hammer 
Caused by builder’s workmanship 
If present in new installation. 
Water supply fixtures 
Does not discharge into the vessel 
Do not discharge into the vessel or leak or drip within 3 months 
Windows and Doors
Installation 
Manufacturer’s instructions 
Deviates from level and plumb >5mm over 1.8m.
Distortion 
Twist or bend greater than limits in Table 8.05 
Exceeds tolerances in Table 11.5 and within 3 months affects the operation of the door.
Glazing 
Scratches and blemishes can be seen from 1.5m 
Scratches and blemishes can be seen from 3m
Plastering
Cracking at junctions of dissimilar materials 
1mm within 12 months
2mm after 12 months 
1mm within 12 months 
Ceiling straightness 
- Deviates >4mm from a 2m straight edge or significantly visible from a normal viewing position within 24 months.
Internal Fixing
Seals around benches
Joint leaks or not to manufacturer’s requirements 

Joint leaks within 6 months or not to manufacturer’s requirements.
Caulking that is inconsistent from a normal viewing position, does not adhere, or contains irregularities.

Sealing of benchtop cut outs
- Timber and porous materials are not adequately sealed to prevent moisture.
Floor & Wall Tiling
Wet area and facilities 
AS 3740 
Water is retained after the area has drained, except for water remaining due to surface tension. 
Leaks from showers which are not intended to prevent the escape of water are not outside tolerance.
Cracked, pitted, chipped, scratched or loose tiles 
Exists at handover or within 24 months 
Exists at completion 
Movement joints
4.5m centres or where stress is expected 
Above structural movement joints and where stress is expected.
Floor Coverings
Wet area and facilities
AS 3740
Water is retained after the area has drained, except for water remaining due to surface tension.
Leaks from showers which are not intended to prevent the escape of water are not outside tolerance.
Cracked, pitted, chipped, scratched or loose tiles 
Exists at handover or within 24 months
Exists at completion
Movement joints 
4.5m centres or where stress is expected 
Above structural movement joints and where stress is expected.
Floor Coverings 
Squeaking floors 
Floors that squeak within 24 months 
Floors and stairs that squeak within 24 months.
Springy floors
Floors that bounce by a person walking normally and substructure is not in accordance with NCC 
Floors that bounce by a person walking normally. 
Decks and Balconies
Leaks in waterproof decks and balconies 
If it leaks 
Leak under normal environmental conditions. 
Wind driven water 
Does not have a drainage system complying with AS 4654.2 
If wind driven water enters the building under normal environmental conditions. 
Exposed timberwork
-  Splits, bows or cups within 3 months of completion under normal environmental conditions.
Eave and external ceiling linings 
- Plaster and lightweight sheeting loose within 12 months of completion or not to manufacturer’s installation instructions.
Landscaping
Water tank 
-  Leaks or not placed on a firm base specified by the manufacturer. Movement identified from a normal viewing position or any overflow washout of the base.
Electrical
Electrical
Does not comply with regulations or contract documents 
A fixture or fitting is out of level from a normal viewing position.
Pools and Spas
Finished height
- Departs from agreed or specified datum by more than ±40mm.
General
Appliances and fittings
Owner is responsible for organising warranty service.
Damage to appliance if due to builder’s workmanship or not fully operational during maintenance period.
Cracked, chipped or scratched,  visible from a normal viewing position at completion, loose, or not fully operational within 3 months of completion. 

To find out more, contact HIA's Building Services team.

Email us

Share with your network:
More articles on:
{{ tag.label }} {{ tag.label }} $vuetify.icons.faTimes
Find the latest expert advice, guides and much more!

The above is intended to provide general information in summary form. The content does not constitute specific advice and should not be relied upon as such. Formal advice should be sought by members and customers with respect to particular matters before taking action.