Enter your email and password to access secured content, members only resources and discount prices.
Did you become a member online? If not, you will need to activate your account to login.
If you are having problems logging in, please call HIA helpdesk on 1300 650 620 during business hours.
If you are having problems logging in, please call HIA helpdesk on 1300 650 620 during business hours.
Enables quick and easy registration for future events or learning and grants access to expert advice and valuable resources.
Enter your details below and create a login
Send me exclusive tips, early access to new launches, and special offers. I can change my mind at any time.
By clicking Get started now you agree to the terms and conditions and privacy policy.
SOPA allows a contractor to:
SOPA allows a person who has undertaken construction work or has supplied related goods and services under a construction contract to make a progress payment claim. Such persons include:
At present, a residential builder cannot make a SOPA claim against their residential owner-client. Disputes with the residential owner-client in relation to such matters will need to either be referred to the Building and Plumbing Commission (BPC) for dispute resolution, or the builder can seek legal advice from a construction lawyer about their contract enforcement options.
The initiating party (the ‘claimant’) is entitled to make one payment claim per month on and from the last day of the month which the work was first carried out. This means, the claimant can submit a claim on 30 April 2026 if the works were first carried out on 1 April 2026.
Whilst the claimant can only submit one claim in one month, they are permitted to roll any outstanding claims from previous months into the next month. For example, if the above example 30 April 2026 claim remains unpaid, the claimant can roll the 30 April 2026 and 29 May 2026 claims together.
The latest a payment claim cannot be served is the later of:
The claimant must ensure that the payment claims contain the following information:
The claimant must serve the payment claim on the respondent (the other party who owes the outstanding amounts) in one of the following methods:
Upon being served the payment claim, the respondent will need to either:
The respondent has 10 business days to serve the claimant with a payment schedule in response to their claimed amount.
A failure to serve the payment schedule within the deadline will result in the claimant being entitled to a payment of the full amount, and this may be recovered in court through a judgment debt process.
The payment schedule will need to include the following information:
The claimant is entitled to pursue the following options if the payment schedule proposes to make a payment lesser than what is claimed or the respondent disputes the claim and does not make any payment at all:
The claimant may choose to lodge an adjudication application with their chosen Authorised Nominating Authorities (ANAs) if:
In addition, the adjudication process further permits the hearing of matters associated with latent defects, time-related costs and any changes affecting regulatory requirements.
However, the respondent will need to ensure that, if a payment schedule is served, it will need to state all the reasons and identify its supporting evidence within the schedule, as the respondent is prohibited from raising any new reasons for withholding payment at adjudication.
The timeframe that a claimant has will depend on the circumstances.
| Respondent fails to serve payment schedule in time | Respondent fails to make payment (full or agreed amount) in time | Claimant disagrees and disputes the proposed payment schedule |
| The claimant has 5 business days to lodge an adjudication application and will have 3 business days to serve on the respondent. |
The claimant has 10 business days to lodge an adjudication application and will have 3 business days to serve on the respondent. | Claimant has 10 business days to lodge an adjudication application and will have 3 business days to serve on the respondent. |
The adjudicator will have 10 business days from the date of appointment, or the date which the respondent lodged an adjudication response – whichever is later – to deliver their determination.
The turnaround timeframe of the determination can be extended to a maximum of 20 business days if it is agreed amongst all parties.
However, the respondent will have 5 business days (or more if agreed to by the adjudicator) to pay the adjudicated amount. Should the respondent fail to make this payment, the claimant can either:
Business day means a day other than:
The definition of business day has been amended to ensure the traditional industry shut-down period over the Christmas and New Years’ break is not calculated to ensure that parties do not inadvertently breach any deadlines.
A notice-based time bar is a construction contract clause requiring a party (usually the contractor) to submit a formal notice within a strict time period. Whilst contracts can include notice-based time bar clauses, SOPA empowers an adjudicator, a court, an arbitrator or an expert determiner the ability to ‘declare’ those time-bar clauses to be ‘unfair’ if compliance would be unreasonably onerous or not reasonably possible.
The decision maker will consider the following in reaching their decision:
The onus of the above factors lies on the party seeking to avoid the time bar (not reading or understanding the terms is not sufficient).
Whether a time bar clause is unfair will be determined on a case-by-case basis. However, if the time bar clause has been declared as invalid, the clause may continue to operate in other circumstances, but it does not invalidate the remainder of the contract.
A construction contract may require a contractor provide a financial security (called a performance security) to the principal to be held until performance under the contract has been met. This financial security can be in the form of:
The above is intended to provide general information in summary form. The content does not constitute specific advice and should not be relied upon as such. Formal advice should be sought by members and customers with respect to particular matters before taking action.
Can’t find what you need, check out other resources that might be closer to the mark.