Enter your email and password to access secured content, members only resources and discount prices.
Did you become a member online? If not, you will need to activate your account to login.
If you are having problems logging in, please call HIA helpdesk on 1300 650 620 during business hours.
If you are having problems logging in, please call HIA helpdesk on 1300 650 620 during business hours.
Enables quick and easy registration for future events or learning and grants access to expert advice and valuable resources.
Enter your details below and create a login
Send me exclusive tips, early access to new launches, and special offers. I can change my mind at any time.
By clicking Get started now you agree to the terms and conditions and privacy policy.
Yes. If you have signed the HIA SA Building Contract for Alterations and Additions dated August 2024, your contract remains compliant.
Several changes have been made to improve the contract including:
The contract now includes a Provisional Sum Item in the building schedule. Previously, the contract only included a schedule for Prime Cost Items.
The "allowances" stated in the Contract Schedule are estimates only and are subject to change. However, it is important to ensure that the allowances are a reasonable estimate of the expected costs. The contract also accounts for a margin to be applied on the excess, if the actual costs exceed the allowance. The maximum margin permitted in South Australia is capped at 15%.
It is important to read Clause 6 of the contract in full (see further below).
This allows builders to specify the interest rate that will apply if the owner is late in making payment. If this section is left blank it will default to the Supreme Court judgement interest rate.
The contract now allows for builders to include any other documents with the intention that they will form part of the contract. The documents listed in this section will be in addition to the standard contract documents which includes any special conditions, general conditions, specifications and plans signed by both the owner and builder.
The date of contract is the date on which the last person signs the contract. This date has now been moved to the Building Schedule, whereas it was previously located on the signature page. The change ensures consistency in how it is referenced throughout the contract.
This Clause was previously called "special meanings." The Clause provides definitions for certain words that are used under the contract. Specifically, any words that are in bold will have a defined meaning under this Clause. This Clause has been updated to include new definitions, for new defined words including:
This Clause expands upon the builder's obligations by requiring:
Clause 3.4 has been updated to specify that the builder cannot claim a progress claim until the works have been completed. This reflects the rules imposed by the relevant legislation. It is important that builders ensure that their administrative practices reflect this requirement.
A new Clause 3.5 permits the builder to reasonably request that the owner provides evidence of their capacity to pay the balance of the contract price.
Clause 4 has been updated to specify that if extra costs are incurred, the builder will provide a written notice within seven days of becoming aware of these additional costs. It requires the owner to pay the additional costs with the next progress claim.
Clause 6 has been rewritten and now sets out the process for:
Clause 10 has been revised to clarify the terms that apply in the event of unlawful early possession by the owner and the actions available to the builder. These actions include treating the owner’s conduct as a repudiation of the contract, issuing a notice to remedy breach, or accepting the early possession as completion of the works as at the date possession was taken.
Clause 11 has been updated requiring the owner to:
If the builder incurs additional costs to gain access, the contract provides that these costs will be passed on to the owner as a variation. The owner's consent is required for this variation, but it must not be unreasonably withheld.
If a finish date is specified in the contract, the builder may extend this date by issuing a written notice. The written notice must specify:
must be provided to the owner as soon as the builder becomes aware of the cause and extent of the delay.
This new clause and the requirement to provide detailed written notice aligns with industry best practices.
New Clauses 12.6 to 12.8 set out the procedures to claim for delay damages. These are the increased costs that the builder may incur due to delays caused by the owner.
To reflect common practice, variations can now be accepted by signing, approving or otherwise consenting to it within 5 days the quote was provided. Approval or consent must be in writing to avoid any disputes later.
Similarly to Clause 13, variations can be accepted by signing, approving or otherwise consenting to it. The contract may be terminated if the owner does not accept the quote provided to comply with the Engineer’s report within seven days.
Previously, if the contract was ended under this Clause, the owner was only liable to pay a maximum amount of $1,650 as payment for the cost of preparing plans, obtaining the Engineer’s report, or conducting any wind assessment, contour plan, or site survey. This Clause has been removed, and the owner must pay the builder the builder’s actual costs.
Clause 34 sets out a new process for termination of contract. In the event of a breach, the Clause now requires that:
As terminating a contract carries significant legal risk, it is essential to seek advice from a solicitor before taking steps to terminate the contract to ensure that you are not in breach of the contract.
This clause introduces a new requirement for the parties to first attempt to jointly appoint a mutually agreed conciliator to assist in resolving the dispute. If the parties cannot reach agreement on a conciliator, HIA may then assist by appointing one on behalf of the parties.
HIA is no longer holding monies in trust on behalf of the dispute referee. Accordingly, HIA will only charge an appointment fee and assist in appointing a dispute referee on behalf of the parties to the contract. The parties shall pay the dispute referee’s fees directly or as otherwise directed by the dispute referee. The appointment fee is currently set at $200 and may be changed from time to time.
This is a new clause which gives the contract documents a priority order. This clause is relied upon if there is conflicting information between the contract documents.
The above is intended to provide general information in summary form. The content does not constitute specific advice and should not be relied upon as such. Formal advice should be sought by members and customers with respect to particular matters before taking action.
Can’t find what you need, check out other resources that might be closer to the mark.