{{ propApi.closeIcon }}
Our industry
Our industry $vuetify.icons.faArrowRight
Housing industry insights Economics Insights Data & forecasts Tailored research & analysis Advocacy & policy Advocacy Policy priorities Position statements Submissions News & inspiration Industry news Member alerts Media releases HOUSING Online
Business support
Business support $vuetify.icons.faArrowRight
For your business Contracts Online Safety systems & solutions HIA Tradepass Advertise jobs Member perks Toyota vehicles The Good Guys Commercial Ampol fuel savings See all Industry insurance HIA Insurance Services Construction works insurance Home warranty insurance Tradies & tool insurance Apprentices Why host a HIA apprentice? Hire an apprentice Support & guidance Contracts & compliance support Building & planning services
Resources & advice
Resources & advice $vuetify.icons.faArrowRight
Building it right Building codes Australian standards Getting it right on site See all Building materials & products Concrete, bricks & walls Getting products approved Use the right products for the job See all Managing your business Dealing with contracts Handling disputes Managing your employees See all Managing your safety Safety rules Working with silica See all Building your business Growing your business Maintaining your business See all Other subjects Getting approval to build Sustainable homes See all
Careers & learning
Careers & learning $vuetify.icons.faArrowRight
A rewarding career Become an apprentice Apprenticeships on offer How do I apply? Frequently asked questions Study with us Find a course to suit you Qualification courses Learning on demand Professional development courses A job in the industry Get your builder's licence Continuing Professional Development (CPD) Further your career Find jobs
HIA community
HIA community $vuetify.icons.faArrowRight
Join HIA Sign me up How do I become a member? What's in it for me? Mates rates Get involved Become an award judge Join a committee Partner with us Our initiatives HIA Building Women GreenSmart Kitchen, bathroom & design hub Get to know us Our members Our people Our partners Support for you Charitable Foundation Mental health program
Awards & events
Awards & events $vuetify.icons.faArrowRight
Awards Awards program People & Business Awards GreenSmart Australian Housing Awards Awards winners Regional Award winners Australian Housing Award winners 2024 Australian Home of the Year Enter online Industry events Events in the next month Economic outlook National Conference Events calendar
HIA shop
HIA shop $vuetify.icons.faArrowRight
Most popular products National Construction Code Vol 1 & 2 Waterproofing wet areas AS 3740:2021 HIA Guide to Waterproofing HIA Guide to NCC Livable Housing Provisions Top categories Building codes & standards Contracts & documents Guides & manuals Safety products Signage For your business Contracts Online Digital Australian Standards Digital Resource Library Forecasts & data
About Contact Newsroom
$vuetify.icons.faTimes
$vuetify.icons.faMapMarker Set my location Use the field below to update your location
Address
Change location
{{propApi.title}}
{{propApi.text}} {{region}} Change location
{{propApi.title}}
{{propApi.successMessage}} {{region}} Change location

$vuetify.icons.faPhone1300 650 620

Dealing with delays in Queensland

HIA is aware that the ongoing impacts of COVID-19 combined with record levels of development activity across Queensland is leading to delays in both the supply of labour and materials.

When should I consider delays?

There will be three stages during a residential building project when you might need to consider how to respond to delays:

  1. Before signing the building contract
  2. After signing the contract but before commencing building work
  3. After building work has commenced

Each stage will present different challenges and, if you do not factor in or respond to delays, you may be liable to compensate the homeowner.

Stage 1. Before signing the building contract

Get the building period right

Ensure you have adequate time under your building period for the completion of the building project. This may mean that you need to:

  • reconsider your usual build times to factor in the current climate
  • be prepared to explain to the homeowner why construction may take longer than usual
  • factor in all foreseeable delays such as annual shut down periods and known delays in the delivery of building materials and
  • be aware of liquidated damages.
    Most contracts provide for a homeowner to be compensated if there are unjustifiable delays during the project. You and the homeowner can agree to this amount.
    If you do not, a default amount may apply or if no amount is specified and there is a dispute, a court or tribunal may determine the appropriate amount.

Consider your current workload

While the current level of interest and activity is appealing, and you don’t want to ‘miss out’ on work, making sure you can deliver on what you commit to should be a priority. 

When assessing your current workload and future commitments you should consider:

  • any limits on your warranty insurance that may impact on the amount of work you can contract for. Investigating this before signing contracts is strongly recommended
  • the availability of subcontractors and
  • predicted delays in the supply of building materials that may impact your local suppliers.

Stage 2. After signing but before commencing building work

Once you have signed the contract you have entered into a legally binding agreement.

Any changes must be made strictly in accordance with the contract.

When should you commence building work?

Under the HIA contract you must commence building work:

  • by the anticipated start date or
  • within 20 working days of the owner fulfilling a number of obligations (such as evidence of land title and a number of other requirements).

If an homeowner does not fulfil their obligations by the anticipated start date, clause 2.2 provides that a builder may end the contract or extend the time for the homeowner to fulfil their requirements.

Commencement has been delayed – what can you do?

You may increase the contract price if commencement has been delayed:

  • more than 4 weeks after the anticipated start date due to a delay that the builder is not responsible for or
  • is caused by the homeowner’s actions.

The price increase may be the reasonable costs incurred because of the delay, or 0.125 percent of the contract price.

Stage 3. After building work has commenced

Delays during construction can be frustrating and cause tension and can also lead to disputes.

To avoid issues and disputes, it is critical that you are aware of your rights and obligations regarding extensions of time.

3 ways to manage delays during the building work

  1. Monitor the progress of the construction work and track it against contracted timeframes.
  2. Communicate any delays or disruptions to the owner as soon as possible.
  3. Seek an extension of time as soon as you become aware that a delay will impact construction timeframes.

How to claim an extension of time

An extension of time may be available if the delay is:

  • caused by something not reasonably foreseeable and beyond the reasonable control of the builder or
  • caused by the owner or
  • caused by a variation of the contract.

There is a non-exhaustive list of what may constitute an extension of time under HIA contracts.

To claim an extension of time you must:

  • provide the owner with a written notice for an extension of time detailing both the cause of the delay and the extension of time required
  • ensure that the notice is provided within 10 working days of when you became aware of both the cause and the extent of the delay and
  • ensure the owner approves the claim in writing.

Once you receive the approved extension of time, a signed copy must be given to the client within 5 working days.

If you do not claim the extension of time in accordance with the contract you may be unable to rely on it.

Generally you cannot claim an extension of time for delays you cause or a delay that was reasonably foreseeable at the time the contract was signed.

The homeowner is disputing an extension of time – what should you do?

Under a HIA contract, a homeowner may dispute an extension of time claim by providing written notice to the builder within 5 working days of receiving the extension of time notice. The homeowner’s written notice must:

  • dispute the extension of time and
  • detail the reason why the extension of time is disputed. 

HIA contracts require the homeowner to not unreasonably refuse to approve an extension of time.

But if the homeowner continues to refuse you have a few options:

  • provide evidence to support your claim.
    Economic information or correspondence from suppliers may help convince a homeowner that the delay was not foreseeable at the time of signing the contract.
  • suspend the building work.
    This is a very serious step and should not be taken without obtaining legal advice.
    In some situations, unlawful suspension of the works may allow a homeowner to terminate the contract.
  • access the Accelerated Builder/Consumer Dispute Framework:
    The Accelerated Builder/Consumer Dispute Framework (ABCD) is a temporary independent mediation service available if you are building a new home or a carrying out a major renovation over $150,000. Applications are free and are subject to certain eligibility requirements. 

Find more information about the ABCD process

You can also contact the Queensland Building and Construction Commission (QBCC) or on 139 333 for further information.

The following information may assist when discussing these issues with a homeowner:

HIA has extension of time documents available through HIA contracts online.

To find out more, contact HIA's Contracts and Compliance team

Email us

Share with your network:
More articles on:
{{ tag.label }} {{ tag.label }} $vuetify.icons.faTimes
Find the latest expert advice, guides and much more!

Managing your business


 

Can’t find what you need, check out other resources that might be closer to the mark.

Explore resources