{{ propApi.closeIcon }}
Our industry
Our industry $vuetify.icons.faArrowRight
Housing industry insights Economics Insights Data & forecasts Tailored research and analysis Advocacy & policy Advocacy Policy priorities Position statements Submissions News and inspiration Industry news Member alerts Media releases HOUSING Online
Business support
Business support $vuetify.icons.faArrowRight
For your business Contracts Online Safety systems & solutions HIA Tradepass Advertise jobs Member perks Toyota vehicles The Good Guys Commercial Ampol fuel savings See all Industry insurance HIA Insurance Services Construction works insurance Home warranty insurance Tradies & tool insurance Apprentices Why host a HIA apprentice? Hire an apprentice Support & guidance Contracts & compliance support Building & planning services
Resources & advice
Resources & advice $vuetify.icons.faArrowRight
Building it right Building codes Australian standards Getting it right on site See all Building materials & products Concrete, bricks & walls Getting products approved Use the right products for the job See all Managing your business Dealing with contracts Handling disputes Managing your employees See all Managing your safety Safety rules Working with silica See all Building your business Growing your business Maintaining your business See all Other subjects Getting approval to build Sustainable homes See all
Careers & learning
Careers & learning $vuetify.icons.faArrowRight
A rewarding career Become an apprentice Apprenticeships on offer How do I apply? Frequently asked questions Study with us Find a course to suit you Qualification courses Learning on demand Professional development courses A job in the industry Get your builder's licence Continuing Professional Development (CPD) Further your career Find jobs
HIA community
HIA community $vuetify.icons.faArrowRight
Join HIA Sign me up How do I become a member? What's in it for me? Mates rates Get involved Become an award judge Join a committee Partner with us Our initiatives HIA Building Women GreenSmart Kitchen, bathroom and design hub Get to know us Our members Our people Our partners Support for you Charitable Foundation Mental health program
Awards & events
Awards & events $vuetify.icons.faArrowRight
Awards Awards program People & Business Awards GreenSmart Australian Housing Awards Awards winners Regional Award winners Australian Housing Award winners 2024 Australian Home of the Year Enter online Industry events Events in the next month Economic outlook National Conference Events calendar
HIA shop
HIA shop $vuetify.icons.faArrowRight
Most popular products National Construction Code Vol 1 & 2 Waterproofing wet areas AS 3740:2021 HIA Guide to Waterproofing HIA Guide to NCC Livable Housing Provisions Top categories Building codes & standards Contracts & documents Guides & manuals Safety products Signage For your business Contracts Online Digital Australian Standards Digital Resource Library Forecasts & data
About Contact Newsroom
$vuetify.icons.faTimes
$vuetify.icons.faMapMarker Set my location Use the field below to update your location
Address
Change location
{{propApi.title}}
{{propApi.text}} {{region}} Change location
{{propApi.title}}
{{propApi.successMessage}} {{region}} Change location

$vuetify.icons.faPhone1300 650 620

Dealing with delays in Tasmania

HIA is aware that the increase in building activity is leading to delays. Here is some information in how to deal with these delays.

The HomeBuilder grant has exceeded all expectations. HIA is aware that this increase in building activity is leading to delays in both the supply of labour and materials.

When should I consider delays?

There will be three stages during a residential building project when you might need to consider how to respond to delays:

  1. Before signing the building contract
  2. After signing the contract but before commencing building work
  3. After building work has commenced

Each stage will present different challenges and, if you do not factor in or respond to delays, you may be liable to compensate your client.

Stage 1. Before signing the building contract

Get the building period right

Ensure you have adequate time under your building period for the completion of the building project. This may mean that you need to:

  • Reconsider your usual build times to factor in the current climate.  
  • Be prepared to explain to your clients why construction may take longer than usual.
  • Factor in all foreseeable delays such as annual shut down periods and known delays in the delivery of building materials.
  • Be aware of liquidated damages.

Most contracts provide for a homeowner to be compensated if there are unjustifiable delays during the project. 

Under the contract you and your client can agree to this amount.

If you do not, a default amount may apply OR if no amount is specified and there is a dispute, a court or tribunal may determine the appropriate amount.

Consider your current workload

While the current level of interest and activity is appealing, and you don’t want to ‘miss out’ on work, making sure you can deliver on what you commit to should be a priority.

This is particularly important given the current requirements regarding commencement timeframes under the HomeBuilder grant.

When assessing your current workload and future commitments you should consider:

  • The availability of subcontractors.
  • Predicted delays in the supply of building materials that may impact your local suppliers.
  • Time period for having a building permit issued.

Stage 2. After signing but before commencing building work

Once you have signed the contract you have entered into a legally binding agreement.

Any changes must be made strictly in accordance with the contract.

When should you commence building work?

Under the HIA contract you must commence building work within 20 working days of the homeowner fulfilling a number of obligations (such as evidence of land title and a number of other requirements).

Commencement has been delayed – what can you do?

If a homeowner does not fulfil their obligations within 20 working days of the date of the contract, clause 10.1 provides that a builder may end the contract or extend the time for the homeowner to fulfil their obligations.

Stage 3. After building work has commenced

Delays during construction can be frustrating and cause tension. 

They can also lead to disputes.

Being aware of your rights and obligations regarding extensions of time is critical.

3 ways to manage delays during the building work

  1. Monitor the progress of the construction work and track it against contracted timeframes.
  2. Communicate any delays or disruptions to the owner as soon as possible.
  3. Seek an extension of time as soon as you become aware that a delay will impact construction timeframes.

How to claim an extension of time

An extension of time may be available if the delay is caused by:

  • something beyond the builder’s sole control, and 
  • the builder suspending the works in accordance with the suspension provisions of the contract.

There is a non-exhaustive list of what may constitute an extension of time under the HIA contracts.

To claim an extension of time you must:

  • Provide the owner with a written notice for an extension of time detailing:
    • The cause of the delay; and
    • The extension of time.
  • Ensure that the notice is provided within 20 working days of when you became aware of both the cause and the extent of the delay.

If you do not claim the extension of time in accordance with the contract you may be unable to rely on it.

Generally you cannot claim an extension of time for delays you cause or a delay that was reasonably foreseeable at the time the contract was signed.

The Homeowner is disputing an Extension of Time – what should you do?

A homeowner may dispute an extension of time.

To dispute the claim, a homeowner must, within 5 working days of receiving the extension of time, provide a written notice to the builder disputing the claim and detailing the reasons why the extension of time is disputed. 

Where a homeowner disputes a request for an extension of time, there are 2 options:

  • Provide evidence to support your claim.
    Economic information or correspondence from suppliers may help convince a client that the delay was not foreseeable at the time of signing the contract.
  • Refer to the dispute resolution clause.
    If you and the homeowner disagree, you should follow the process set out in the dispute resolution clause of the contract.

HIA has extension of time documents available through HIA contracts online.

To find out more, contact HIA's Contracts and Compliance team

Email us

Share with your network:
More articles on:
{{ tag.label }} {{ tag.label }} $vuetify.icons.faTimes
Find the latest expert advice, guides and much more!

Managing your business


 

Can’t find what you need, check out other resources that might be closer to the mark.

Explore resources

Become a HIA member today

Join Australia’s largest residential building association to gain access to a huge range of industry products and business services. We can help you manage, operate and grow your business.

TAS Residential Building Contract (Pack of 2)

The Tasmanian Domestic Building Contract (pack of two) is tailored to meet state legislation, but is a plain language document so it's easy to understand. The contract covers new homes, domestic alterations, additions and renovati...

TAS Minor Works Contract (Pad of 25)

The Tasmania Minor Works Contract Pad is suitable for minor residential building works up to a value of $12,000. It’s available in a handy tear-off pad of 25. This is a hard copy document and will be mailed to you once it's purcha...

TAS Job Quotation Form

The Tasmanian Job Quotation Form is suitable for sub-contractors to list their conditions. It's carbonised and individually numbered and dated.

TAS Kitchen Bathroom & Laundry Supply Install under $20K

The Supply & Install Contract is tailored specifically to the kitchen, bathroom and laundry industry for work under $20,000. The contract allows for all job details to be formalised and facilitates an estimate of pricing for provi...

TAS Kitchen Bathroom & Laundry Supply Install over $20K

The Supply & Install Contract is tailored specifically to the kitchen, bathroom and laundry industry for work over $20,000. The contract allows for all job details to be formalised and facilitates an estimate of pricing for provis...

TAS Notice of Commencement - New Homes (Pad of 25)

The Notice of Commencement – New Homes (pad of 25) is used to advise the owner that the builder has started works and what's required under the provisions of the Tasmanian Domestic Building Contract. This is a hard copy version of...

TAS Final Inspection Notice (Pad of 25)

The Tasmanian Notice of Completion (pad of 25) is used to formally notify an owner when a project will be at practical completion. It's designed for use with HIA contracts. Note: This form is specific to Tasmania and shouldn't be ...

TAS Progress Claim Certificate (Pad of 25)

The Tasmanian Progress Claim Certificate (pad of 25) provides an efficient way for a builder to claim payment from a client or financial institution. This is a hard copy version of the certificate and will be mailed to you once i...