Enter your email and password to access secured content, members only resources and discount prices.
Did you become a member online? If not, you will need to activate your account to login.
If you are having problems logging in, please call HIA helpdesk on 1300 650 620 during business hours.
If you are having problems logging in, please call HIA helpdesk on 1300 650 620 during business hours.
Enables quick and easy registration for future events or learning and grants access to expert advice and valuable resources.
Enter your details below and create a login
Prime cost (PC) items are fixtures and fittings or individual articles and appliances that the owner is to select after the signing of the contract such as a kitchen vanity or tapware. Provisional sum (PS) items are work that the builder cannot provide a definite price for at the time of signing the contract. This might include excavation, rock removal or labour for tiling.
At the time of filling out the contract, an allowance for a PC or PS Item will be entered into the table. This allowance must be a reasonable estimate of what the builder believes the item or work will cost, based on the information that the builder has at the time of entering into the contract. The allowance in the table does not include the builder’s margin.
What the builder must do is ensure that the margin to be applied to the allowance for that item is included in the contract price before signing the contract. The margin will then be received at each progress stage within the progress claim.
The builder does not have to disclose this margin to the owner.
A common mistake that builders make is to charge the owner the “20% margin on excess” on the whole amount of the actual cost of a PC or PS Item after they have completed the work. This is incorrect and may lead to an owner refusing to pay the margin.
If the actual cost of an item exceeds what the builder has allowed for it, under the HIA Contract the builder can claim the actual cost of the item, the excess, plus a margin of 20% on that excess. This amount will be claimed at the next progress stage and the builder must ensure that the owner is given evidence of the cost of the item.
Remember that the margin on the original allowance will already be received by the builder at each progress stage.
In this scenario, the builder simply credits the difference between the actual cost of the item and the allowance to the owner in the next progress claim.
If an owner requests that the builder remove or omit a PC or PS item from the contract, the builder must ensure that this variation is put into writing. The amount of the allowance as shown in the PC and PS Item table is to be credited back to the owner in the next progress claim.
The builder does not have to credit the builder’s margin for that item back to the owner.
The builder is required to provide the owner with evidence of the cost of the PC or PS item when requesting payment for the item.
If the allowance in schedule 3 is $1100 (including GST) and the percentage on excess is 20%
Foundations data is the information (for example soil testing) relevant to a building site that a building contractor requires in order to prepare a footing and/or concrete slab design for the building site, and also to establish the cost of the foundations component of the works.
Failure to obtain foundations data prior to entering into a contract is an offence under the Queensland Building and Construction Commission Act (QBCC Act) unless an exemption applies. The exemption applies if you:
If you have obtained foundations data before entering into your contract you can list excavation (or earthworks) as a provisional sum in which case the above rules for provisional sums apply.
Can’t find what you need, check out other resources that might be closer to the mark.