{{ propApi.searchIcon }}
{{ propApi.closeIcon }}
Our industry
Our industry $vuetify.icons.faArrowRight
Housing industry insights Economics Insights Data & forecasts Tailored research & analysis Advocacy & policy Advocacy Policy priorities Position statements Submissions News & inspiration Industry news Member alerts Media releases HOUSING Online
Business support
Business support $vuetify.icons.faArrowRight
For your business Contracts Online Safety systems & solutions Advertise jobs HIA SafeScan Member perks Toyota vehicles The Good Guys Commercial Ampol fuel savings See all Industry insurance HIA Insurance Services Construction works insurance Home warranty insurance Tradies & tool insurance Apprentices Why host a HIA apprentice? Hire an apprentice Support & guidance Contracts & compliance support Building & planning services
Resources & advice
Resources & advice $vuetify.icons.faArrowRight
Building it right Building codes Australian standards Getting it right on site See all Building materials & products Concrete, bricks & walls Getting products approved Use the right products for the job See all Managing your business Dealing with contracts Handling disputes Managing your employees See all Managing your safety Safety rules Working with silica See all Building your business Growing your business Communication for your business See all Other subjects Getting approval to build Sustainable homes See all
Careers & learning
Careers & learning $vuetify.icons.faArrowRight
A rewarding career Become an apprentice Apprenticeships on offer How do I apply? Frequently asked questions Study with us Find a course to suit you Qualification courses Learning on demand Professional development courses A job in the industry Get your builder's licence Continuing Professional Development (CPD) Further your career Find jobs
HIA community
HIA community $vuetify.icons.faArrowRight
Join HIA Sign me up How do I become a member? What's in it for me? Mates rates Our podcasts Made To Build Built Different HIA Building Australia Building the Hunter Our initiatives HIA Building Women GreenSmart Kitchen, bathroom & design hub Get involved Become an award judge Join a committee Partner with us Support for you Charitable Foundation Mental health program Get to know us Our members Our people
Awards & events
Awards & events $vuetify.icons.faArrowRight
Awards Awards program People & Business Awards GreenSmart Australian Housing Awards Awards winners Regional Award winners Australian Housing Award winners 2025 Australian Home of the Year Enter online Industry events Events in the next month Economic outlook National Conference Events calendar
HIA shop
HIA shop $vuetify.icons.faArrowRight
Most popular products National Construction Code Vol 1 & 2 Waterproofing wet areas AS 3740:2021 HIA Guide to Waterproofing HIA Guide to NCC Livable Housing Provisions Top categories Building codes & standards Contracts & documents Guides & manuals Safety products Signage For your business Contracts Online Digital Australian Standards Digital Resource Library Forecasts & data
About Contact Newsroom
$vuetify.icons.faTimes
$vuetify.icons.faMapMarker Set my location Use the field below to update your location
Address
Change location
{{propApi.title}}
{{propApi.text}} {{region}} Change location
{{propApi.title}}
{{propApi.successMessage}} {{region}} Change location

$vuetify.icons.faPhone1300 650 620

Prime cost provision sums and residential building contracts for new dwellings

A prime cost (PC) item is an item that, at the time of the contract, is not selected but is to be selected by the owner. A PC allowance is the cost to the owner for the supply of the item only. A PC does not include any installation cost or the costs of other work related to the PC. Provisional sums (PS) have a much wider application and are used where there is a mixture of items and labour (installation). A PS is not to be used where the relevant item is for supply only.

Prime cost items (PCs)

Typical examples of a PC include ‘white goods such as cooktops and ovens’, ‘bathware’ such as vanities, baths and tapwear, door and door furniture such as handles and ‘floor coverings’ such as tiles. 

There is no legislation in NSW directly regulating the use of PCs and the HIA contract follows accepted industry practice. 

Prime cost items and the contract 

Clause 21.4 of the contract requires that ‘each prime cost must have an allowance stated next to it. The allowance is the estimated price to supply the item and does not include an amount for the builder’s margin’. 

This means the PC allowance is the estimated cost price for the builder to supply the item to the owner. The price of the PC to the owner is the actual cost price plus the builder’s margin applied to the amount by which the actual cost price exceeds the PC allowance. 

Normal prime cost adjustments 

PCs are not normally treated as variations. The adjustment calculation should be prepared on an invoice that is to be paid in accordance with Clause 21.7. However, there are exceptions as detailed below. The calculation is set out in Clause 21.6 of the contract which provides that:

‘‘In relation to each prime cost item and provisional sum item if the actual price is: 

(a) less than the allowance, the difference is deducted from the contract price, and
(b) more than the allowance, the total of the difference and the builder’s margin applies to that difference is added to the contract price.” 

Example:
If there is an upgrade or downgrade to a PC and the PC remains within its general specification then the pricing calculation would be as per clause 21.6 of the contract. That is to say if a selected electric cooktop is more expensive than the allowance, then the price to the owner is the actual cost price, plus the builder margin applied to the amount by which the actual cost price exceeds the PC allowance. 

When does a PC become a variation? 

Changing a specification to a new specification is not a PC adjustment, it’s a variation. 

Example:

  • If the owner decided to change the PC described as an ‘electric cooktop’ to a ‘gas cooktop’ (which included the laying of gas lines and certification of gas installation), then this is no longer something that can be calculated as a PC. It is a variation. The calculation would now include the price of the new cooktop plus any installation costs less the PC allowance. 
  • The contract has a PC for tiles with standard laying. The owner decides to purchase different tiles from the specifications, which require different laying and bonding requirements, This is a variation as to the scope of work. The actual tile price may be calculated as a PC adjustment but, in addition, a variation is required due to the additional work. 

Provisional sum items (PSs)

PSs are often confused with PCs. PSs have a much wider application and are used where there is a mixture of items and labour (installation). A PS is not to be used where the relevant item is for supply only. 

Examples of PSs

Pools where the owner has not decided on the construction method. A pergola where the owner has not decided on the construction method or size. Paths and driveways where the materials, shape, size and finish has not been decided. Kitchens with white goods and tiling. Tile and carpet and other floor covering and light fitting with fans and security lights that are not specified. 

Provisional sums and the contract 

Clause 21.5 of the contract provides that ‘each provisional sum item must have an allowance stated next to it. The allowance is the estimated price of providing the work and does not include an amount for the builder’s margin’. 

The essential difference between a PS and a PC is that PSs involved work, where PCs are items only. This means the PS allowance is the estimated cost price for the builder to do the work (item plus labour) for the owner. The price of the PS to the owner is the actual cost price plus the builder’s margin applied to the amount by which the actual cost price exceeds the PS allowance. 

Normal provisional sum adjustments 

PSs are not treated as variations. The adjustment calculation should be prepared on an invoice that is to be paid in accordance with Clause 21.7. 

The calculation is set out in clause 21.6 of the contract which provides that: 

‘In relation to each prime cost item and provisional sum item if the actual price is:
(b) less than the allowance, the difference is deducted from the contract price, and
(c) more than the allowance, the total of the difference and the builder’s margin applies to that difference is added to the contract price.’ 

PSs are normally not variations 

The owner can choose whatever work they want within the range of work contemplated by the PS description. Therefore, unlike a PC item, where there is a change to the scope of work, there is no need to do a variation. 

Example: 

The contract contains a PS for ‘the supply and installation of an kitchen cooktop’. If the owner selects a gas cooktop (which includes the laying of gas lines and certification of gas installation), then all the costs are calculated as a PS and if there is a positive difference in the actual cost price over the allowance, then the builder’s margin is added to that difference. 

In summary, if you are in dispute with an owner over PC and PS allowances or calculations, the HIA recommends you contact HIA Workplace Services or your solicitor for advice on your particular circumstances. 

Share with your network:
More articles on:
{{ tag.label }} {{ tag.label }} $vuetify.icons.faTimes
Find the latest expert advice, guides and much more!

Managing your business


 

Can’t find what you need, check out other resources that might be closer to the mark.

Explore resources

No products available