{{ propApi.closeIcon }}
Our industry
Our industry $vuetify.icons.faArrowRight
Economic research & forecasting Economics Housing outlook Economic reports & data Tailored market research Advocacy & policy Advocacy Policy priorities Position statements Submissions News and inspiration Industry news Member alerts Media releases HOUSING Online
Business support
Business support $vuetify.icons.faArrowRight
Become an apprentice host Hire an apprentice Why host a HIA apprentice? Apprentice partner program Builder & manufacturer program Industry insurance Construction legal expenses insurance Construction works insurance Home warranty insurance Tradies & tool insurance Planning & safety solutions Building & planning services How can safety solutions help you? Independent site inspections Solutions for your business Contracts Online HIA Tradepass HIA SafeScan Advertise jobs Trusted support & guidance Contracts & compliance support Professional services Industrial relations Member savings Toyota vehicles The Good Guys Commercial Fuel savings See all
Resources & advice
Resources & advice $vuetify.icons.faArrowRight
Building it right Building codes Australian standards Getting it right on site See all Building materials & products Concrete, bricks & walls Getting products approved Use the right products for the job See all Managing your business Dealing with contracts Handling disputes Managing your employees See all Managing your safety Falls from heights Safety rules Working with silica See all Building your business Growing your business Maintaining your business See all Other subjects COVID-19 Getting approval to build Sustainable homes See all
Careers & learning
Careers & learning $vuetify.icons.faArrowRight
A rewarding career Become an apprentice Apprenticeships on offer Frequently asked questions Study with us Find a course to suit you Qualification courses Learning on demand A job in the industry Get your builder's licence Continuing Professional Development (CPD) Find jobs
HIA community
HIA community $vuetify.icons.faArrowRight
Join HIA Sign me up How do I become a member? What's in it for me? Mates rates Get involved Become an award judge Join a committee Partner with us Our initiatives HIA Building Women GreenSmart Kitchen, bathroom and design hub Get to know us Our members Our people Our partners Support for you Charitable Foundation Mental health program
Awards & events
Awards & events $vuetify.icons.faArrowRight
Awards Awards program People & Business Awards GreenSmart Australian Housing Awards Awards winners Regional Award winners Australian Housing Award winners 2023 Australian Home of the Year Enter online Industry events Events in the next month Economic outlook National Conference Events calendar
HIA products
HIA products $vuetify.icons.faArrowRight
Shop @ HIA Digital Australian Standards Contracts Online Shipping & delivery Purchasing T&Cs See all Products Purchase NCC 2022 Building codes & standards Economic reports Hard copy contracts Guides & manuals
About Contact Newsroom
$vuetify.icons.faTimes
$vuetify.icons.faMapMarker Set my location Use the field below to update your location
Address
Change location
{{propApi.title}}
{{propApi.text}} {{region}} Change location
{{propApi.title}}
{{propApi.successMessage}} {{region}} Change location

$vuetify.icons.faPhone1300 650 620

Guide to getting paid

At times, building contractors in Queensland have difficulty getting paid, particularly by homeowners. Owners may withhold the final payment or attempt to “negotiate” the final payment based on minor defects. This puts undue pressure on building contractors.

To assist with getting paid, we recommend the following: 

  1. Ensure you notify the owner in writing that practical completion has been reached as per the contract requirements;
  2. Do a final walkthrough with the owner. At this walkthrough, listen to the owner and their complaints (if any) regarding alleged defects. If the owner has concerns, try to address them then and there, then develop the defects document required for practical completion. Do not be afraid to discuss payment and be upfront with your expectations for payment;
  3. Advise the owners that, in accordance with the HIA contract, you will not be providing them with the keys to the property until you are paid in full. Ensure the site is secure during this period;
  4. Remind the owner that there is a statutory 12 month defect liability period. If the owner is genuinely concerned as to whether an item is defective, they always have the option of involving the QBCC;
  5. If payment is more than five days late, we would suggest you send a first letter of demand. Follow this letter up with a phone call. If necessary, offer to have another onsite meeting to go through any issues; and
  6. If the owner still refuses to pay, the builder has the option of commencing proceedings with the QBCC Early Dispute Resolution (EDR) process, and thereafter if needed the Queensland Civil and Administrative Tribunal (QCAT). This is obviously the last resort but it is the only forum that building contractors can really commence proceedings in.

The single best tip in getting paid is to ensure that your contract administration is carried out properly from the commencement of the contract.

To find out more, contact HIA's Workplace Services team

Email us

Share with your network:
More articles on:
{{ tag.label }} {{ tag.label }} $vuetify.icons.faTimes
Find the latest expert advice, guides and much more!

Managing your business


 

Can’t find what you need, check out other resources that might be closer to the mark.

Explore resources

Contracts Online 


 

The industry’s go-to digital platform. 

No matter the size of the job, a watertight building contract is critical to protect your business, and the current climate presents a great opportunity to go digital with your contracts.

Take me there